Let’s assume a typical case where you need to concrete a floor for that day.
You have to instruct the labourers to bring the required materials from the stock room for the day or you need to buy materials from the store.
In these two scenarios, you need to know the exact material requirements for the concrete volume, if not either you have to bring/buy more materials interrupting the work or you will do partial work. Where the manpower will be totally wasted and impact your cost estimation.
So today’s post, we are going to know How to calculate Cement bags per Cubic meter Concrete? For Nominal Mix
Assume the following case,
If you fill the shuttering area with blue metal alone it has lots of voids in it which also need to be filled by the other materials such as sand & cement. Such void gap is known as void ratio compressibility which is 30-32% for coarse aggregate & 20% for sand.
So if we need 1 m3 of concrete in wet condition we have to take consideration of the bulking of sand and void ratio compressibility for both coarse & fine aggregate (32%+20%) = 52%
Adding 3% as wastage it comes as 55%.
Thus every time you need to calculate the volume of concrete you need to add the above percentage with dry volume
Wet Volume of concrete = Dry Volume of concrete + 55% of dry volume of concrete or
Wet Volume of concrete = Dry Volume of concrete x 1.55
So whatever volume we get from the above formula, we need to multiply the value with 1.55%
We already discussed the volume formula from Concrete Volume Calculation which is
Required Cement Quantity for 1 m3 = (Cement Part / Total Parts) x 1.55 = 1/(1+2+4) x 1.55 = 0.221 m3
Unit weight of cement = 1440 kg / m3
Therefore required cement = 1440 x 0.221 m3 = 318.24 Kg or (318.24/50) = 6.37 Bags
Cement Bag Per Cubic Metre Concrete Table – Nominal Mix
Concrete Grade | Mix Ratio | Cement in Cubic metre | Cement in Bags |
M5 | 1:5:10 | 0.097 | 2.79 |
M7.5 | 1:4:8 | 0.119 | 3.43 |
M10 | 1:3:6 | 0.155 | 4.46 |
M15 | 1:2:4 | 0.221 | 6.37 |
M20 | 1:1.5:3 | 0.282 | 8.12 |
Happy Learning 🙂
Before starting any civil engineering work, regardless of branches, horizontal, vertical, and angular measurements of…
The data measurements gathered from surveying helps establish the plan and design of all civil…
Surveying is the art and science of civil engineering that determines the relative (comparable) position…
The formation of cracks on the concrete surface may lead to reduce the durability of…
Understanding the different levels of structure seems a bit of a daunting task. Don’t worry…
We knew that pipes are used to transport gas or liquid substance from one place…