How to Calculate Cement bags per Cubic meter Concrete?

Let’s assume a typical case where you need to concrete a floor for that day. 

You have to instruct the labourers to bring the required materials from the stock room for the day or you need to buy materials from the store.

In these two scenarios, you need to know the exact material requirements for the concrete volume, if not either you have to bring/buy more materials interrupting the work or you will do partial work. Where the manpower will be totally wasted and impact your cost estimation.

So today’s post, we are going to know How to calculate Cement bags per Cubic meter Concrete? For Nominal Mix

Procedure For Calculating Material Quantity In 1 Cubic Meter Of Concrete

Assume the following case,

  • Nominal Mix Ratio is 1:2:4
  • Void Ratio Compressibility 52%
  • Wastage is 3%
  • Density of Cement – 1440 kg / m3

Void Ratio Compressibility

If you fill the shuttering area with blue metal alone it has lots of voids in it which also need to be filled by the other materials such as sand & cement. Such void gap is known as void ratio compressibility which is 30-32% for coarse aggregate & 20% for sand.

So if we need 1 m3 of concrete in wet condition we have to take consideration of the bulking of sand and void ratio compressibility for both coarse & fine aggregate (32%+20%) = 52%

Adding 3% as wastage it comes as 55%.

Thus every time you need to calculate the volume of concrete you need to add the above percentage with dry volume

Wet Volume of concrete = Dry Volume of concrete + 55% of dry volume of concrete or

Wet Volume of concrete = Dry Volume of concrete x 1.55

So whatever volume we get from the above formula, we need to multiply the value with 1.55%

Calculation

We already discussed the volume formula from Concrete Volume Calculation which is

Required Cement Quantity for 1 m3 = (Cement Part / Total Parts) x 1.55 = 1/(1+2+4) x 1.55 = 0.221 m3

Unit weight of cement = 1440 kg / m3

Therefore required cement = 1440 x 0.221 m3 = 318.24 Kg or (318.24/50) = 6.37 Bags

Cement Bag Per Cubic Metre Concrete Table – Nominal Mix

Concrete Grade Mix Ratio Cement in Cubic metre Cement in Bags
M5 1:5:10 0.097 2.79
M7.5 1:4:8 0.119 3.43
M10 1:3:6 0.155 4.46
M15 1:2:4 0.221 6.37
M20 1:1.5:3 0.282 8.12

Happy Learning 🙂

Bala

Bala is a Planning Engineer & he is the author and editor of Civil Planets.

Share
Published by
Bala

Recent Posts

Uses of Surveying

Before starting any civil engineering work, regardless of branches, horizontal, vertical, and angular measurements of…

2 years ago

Importance of Surveying

The data measurements gathered from surveying helps establish the plan and design of all civil…

2 years ago

What is Surveying?

Surveying is the art and science of civil engineering that determines the relative (comparable) position…

2 years ago

What is Grouting? – Types & Applications

The formation of cracks on the concrete surface may lead to reduce the durability of…

3 years ago

Difference Between Plinth Level, Sill Level, and Lintel Level

Understanding the different levels of structure seems a bit of a daunting task. Don’t worry…

4 years ago

What is Prestressed Concrete Pipe?

We knew that pipes are used to transport gas or liquid substance from one place…

4 years ago