Labour Requirement for Civil Works

In a project budget, the toughest thing is to identify the source of material and required manpower calculation. We have to deploy adequate manpower to complete a certain activity without any chaos.

In this post, we had listed out the approx labour requirement for civil works and also Labour output per day for different works. 

In the earlier post, we had seen the material calculation for different construction work.

Labour Requirement for Civil Works

Scope of Work Labour Requirement Quantity (Nos)
Excavation up to 1.5m Depth including disposal of soil lead up to 50m- 28.3 m3 – Soft Rock Mason 0.15
Male Coolie 5
Female coolie 4
Excavation Upto 1.5m Depth including disposal of soil lead up to 50m- 28.3 m3 – Soft Rock Mason 0.15
Male Coolie 6.5
Female coolie 5
Excavation Upto 1.5m Depth including disposal of soil lead up to 50m- 28.3 m3 – Soft Rock Mason 0.2
Male Coolie 8
Female coolie 6
Soil backfilling including watering and hammering – 10 m3 Male Coolie 1.5
Female coolie 1.35
Plain Cement Concrete – 1 m3 Male Coolie 0.7
Female coolie 0.7
Mason 0.13
Foreman 0.13
Reinforced Cement Concrete – 1 m3 Male Coolie 1
Female coolie 1
Mason 0.3
Foreman 0.15
Formwork – 11.16 Sqm including  fixing and deshuttering Carpenter 2.25
Foreman 0.2
Helper 2.25
Brick Masonry – 1 m3 Mason 0.4
Male Coolie 0.5
Female coolie 0.5
Waterman 0.2
Half Brick Masonry -10 Sqm Mason 0.9
Male Coolie 0.6
Female coolie 0.4
Waterman 0.2
Solid Block Masonry -1.89 m3 Mason 2.5
Male Coolie 1.75
Female coolie 1.75
Waterman 0.2
Concrete Flooring 25mm Thk 10 Sqm Mason 1
Male Coolie 1
Female coolie 1
Waterman 0.1
Tile Skirting on Steps and dados – 1 Sqm Mason 0.6
Male Coolie 0.5
Waterman 0.25
Tile Flooring – 1 Sqm Mason 0.4
Male Coolie 0.4
Waterman 0.1
Smooth Finish Plastering – 10 Sqm and 12mm Thk Mason 0.75
Male Coolie 1.5
Female coolie 1.5
Waterman 0.15
Distemper Painting including Prime coat – 10 Sqm Painter 0.45
Helper 0.45
Steel reinforcement – 100 Kg including cutting and laying Barbender 0.8
Helper 0.8

Labour Output per day in Construction

Manpower  Activity Output (8 Hours)
Mason – 1
Male mazdoor – 0.75
Female Mazdoor – 0.5
Brick Work 45 Cft
Mason – 1
Male mazdoor – 1
Female Mazdoor – 0.5
Wall plastering 120 Sft
Mason – 1
Male mazdoor – 0.75
Female Mazdoor – 0.5
Ceiling Plastering 90 Sft
Carpenter-2.25
Foreman- 0.2
Helper- 2.25
Shuttering Work 11 Sqm
Bar Bender – 1 Nos
Helper – 1 Nos
Steel Work 100 Kg
Tile Mason – 1 Nos
Helper – 1 Nos
Tile Work 10 Sqm
Mason – 2
Male mazdoor – 1.75
Female Mazdoor – 1.75
Block Work 2 m3
Male Coolie – 5 Nos
Female Coolie – 4 Nos
Earth Digging 1000 Cft

If you want to update the manpower adequacy, then don’t forget to comment.

Bala

Bala is a Planning Engineer & he is the author and editor of Civil Planets.

View Comments

Share
Published by
Bala

Recent Posts

Uses of Surveying

Before starting any civil engineering work, regardless of branches, horizontal, vertical, and angular measurements of…

2 years ago

Importance of Surveying

The data measurements gathered from surveying helps establish the plan and design of all civil…

2 years ago

What is Surveying?

Surveying is the art and science of civil engineering that determines the relative (comparable) position…

2 years ago

What is Grouting? – Types & Applications

The formation of cracks on the concrete surface may lead to reduce the durability of…

3 years ago

Difference Between Plinth Level, Sill Level, and Lintel Level

Understanding the different levels of structure seems a bit of a daunting task. Don’t worry…

4 years ago

What is Prestressed Concrete Pipe?

We knew that pipes are used to transport gas or liquid substance from one place…

4 years ago