Today we are going to discuss brickwork calculation. We are going to find out the below for 1m3 of brickwork

  • Number of bricks
  • Required cement quantity
  • Required sand quantity

Brickwork Basics

  • Size of the Bricks – 190mm x 90mm x 90mm 

brickwork calculation

For calculation, purposes convert the Size of bricks into Meter.

So now the measurement is 0.19m x 0.09m x 0.09m

Therefore Volume of 1 brick = 0.001539 m3

Brickwork Calculation Formula

STEP 1 – Volume of single brick without mortar

Volume of 1 brick without mortar  = 0.19 x  0.09  x 0.09 = 0.0015 m3              

STEP 2 – Volume of single brick with mortar

While brickwork construction we will add cement mortar around 3 sides (left, right & top). 

So adding 10mm thick on each side of brick as mortar thickness 

The volume of brick with mortar = (0.19+0.010) x (0.09+0.010) x (0.09+0.010) =  0.20 x 0.1 x 0.1  = 0.002 m3 

The volume of 1 brick with mortar = 0.002 m3

STEP 3 – Number of bricks for 1 m3 Brickwork

Number of bricks with mortar for 1 m3 = 1 cubic meter / volume of bricks with mortar = (1/0.002)= 500 Nos

So the required number of bricks for 1 m3 = 500 Nos

STEP 4 – Cement Mortar Volume for 1m3 of Brickwork

Cement Mortar Volume = Volume of brickwork with mortar – the volume of bricks without mortar

Volume of bricks with mortar in 1 m3 = 500 x 0.002 = 1 m3

Volume of bricks without mortar in 1 m3 = 500 x 0.001539 = 0. 7695 m3

Therefore required cement mortar = 1 m3 – 0.7695 m3 = 0.2305 m3

Step 5 – Calculate Cement & Sand Volume

As we know the required cement mortar = 0.2305 m3

Assuming cement mortar ratio as 1:5 (1 Part Cement: 5 Part Sand)

We have already discussed the cement mortar volume calculation in the plastering work post.

plastering calculation formula

The above formula will give the dry volume of cement mortar, So to get wet concrete volume, we have to multiply the dry volume by 1.55 

Total Parts = 1+5 =6

Required Volume of Cement = 1/6 x 1.55 (void ratio) x Mortar Volume = 1/6 x 1.55 x 0.2305= 0.0595 m3

To convert into cement bags  – (0.0595 x 1440)/50 = 1.71 Bags or 85.68 Kg 

Required Sand Volume = 5/6 x 1.55 (void ratio) x Mortar Volume = 5/6 x 1.55 x 0.2305 = 0.298 m3

Result

Materials required for 1 m3 Brickwork is

  • 500 Numbers of bricks
  • 85.68 kg or 1.71 Bags of cement
  • 0.298 m3 of sand

Make Use of this brickwork calculator

Hope you learned something from this post. Happy day 🙂

Author

Bala is a Planning Engineer & he is the author and editor of Civil Planets.

1 Comment

  1. For cement mortar the dry volume factor to be considered is 1.33 not 1.55